Problem:
The same automotive component was being placed in the same orientation in 2 different welding cells
Cycle time was nearly double what it would have been if all welds were completed in one cell
Mirror image parts could not be made in tandem, requiring lengthy switchover times between production batches
This cell merge was the bottleneck for future factory cell efficiency updates
Role:
The third co-op student assigned this task after the previous 2 terms' students did not come to a viable solution
Took the design from scratch to engineering drawings
Constraints:
New tooling must not interfere with either weld process
Repurpose existing tooling
Save material cost where possible
Successfully merged two factory cells through new tooling design and procedural updates
Saved $100,000/year through labour reallocation
Nearly 2x station efficiency
Saved >$8,000 in material cost on weld plate through the implementation of a multi-material insulated design
Minimized part handling in production
Design Process:
Designed tooling to be compatible with both mirror images of the part
Added another lower welding electrode without causing an interference
Adding movement to the entire tooling plate through pneumatic cylinders, enabling weld alignment without requiring an additional spot welder
Manufacturing Considerations:
Instead of creating an entire plate from copper, copper was only added underneath the lower welding electrodes
Copper portion is nested in an insulated layer and within a cheaper aluminum plate
My first large engineering project showed me how to work with what I was given to minimize costs and maintain functionality. While also giving me the confidence to see that I could figure out problems others could not, even on my first co-op term.